|
In 1995, 2
prefeasibility studies were conducted based on parabolic trough and central
tower technologies.
In 1996, a SolarPACES START Mission was requested by
the hosting New and Renewable Energy Agency (NREA) and the Egyptian Electric
Authority (EEA) of the Government of Egypt, to provide information exchange
by independent experts on solar thermal technologies applicable in Egypt.
The START Mission recommendations served as the information basis and
independent expert evaluation for Egypt’s subsequent application to the
Global Environmental Facility, to support the identified 130MW Hybrid Fossil
Solar Thermal (HFST) Power plant project at Kuraymat with private
participation with a 50Mio USD support grant under GEF-OP7.
In 1996,
it was agreed to implement the 1st solar thermal power plant.
GEF granted
the project consultancy services and expressed the willingness to cover the
incremental cost. In 1998, the conceptual design and project concept paper
were prepared. The consultancy services were divided into 2 phases. In 2000,
the 1st phase was conducted and ended up by Issuing complete feasibility
study report. A short list for the qualified and interested developers was
set up. Due to the unexpected high rate of US$ exchange against LE and to
avoid the lack of foreign currency in 2002, the government issued
regulations for BOOT projects to minimize the burden on the national
treasury and reduce the envisaged risks. The new regulations could be
briefed as follows:
-
The required financing and its
related annual cost shall be in local currency.
-
The project financing can be in
foreign currency, on condition that the annual re-payments shall be from
export revenues achieved by the project.
In May 2003, A study was conducted
by WB to assess the level of interest of the developers, in view of the a/m
regulations. The outcomes were negative. In June 2003, NREA and World Bank
agreed upon changing the approach of the project to be a governmental one.
The private sector could participate in the
O&M through a contract limited
by 5 years. In Oct. 2003, a contract was signed with Fichtner Solar to
conduct the 2nd phase of Consultancy services in view of the a/m approach.
The new technical data of the project could be briefed as follows:
|
Total capacity
|
150 MW |
|
Solar contribution |
30 MWe |
|
Solar share |
6.6 % / a of the produced
energy |
|
Avoided emmissions |
37000 T CO2 / a |
|
Investment cost |
US$ Mio 150 million |
|
Incremental cost |
US$ Mio 50 million |
A general Procurement Notice was
published in Feb. 2004. The Notice is addressed to interested bidders,
interested consultants and any other interested entities request for
additional information. 35 firms expressed their interest to be enrolled in
the mailing list for PQD. In March 2004, the draft of the conceptual design
report was sent to NREA for review together with a PQD draft for review and
comment.
GEF has
allocated a grant of nearly US$ 50m to cover the incremental cost in May
2004 and JBIC has expressed the interest to finance the balance of the
plant. The project will be owned by NREA. There will be a role for the
private sector through
EPC, O&M contract for 5 years. NREA is in the phase
of preparing Pre-Qualification Document and Tender Document. A General
Procurement Notice addressed to the interested bidders & consultant was
issued in Worldbank News letter in February 2004. 35 firms expressed the
interest to be enrolled in the mailing list for the Request for
Prequalification. The prequalification document and the Bid Document had
been completed by August 2004. In parallel NREA had investigated potential
sources of co-financing. On request of the financing institutiond the
existing turnkey Bid Document in 2005 was split into two Bid Documents (one
for the Solar Island and another one for the combined Cycle Island).
Fichtner is currently working to prepare these two Bid Documents. On
August 16th 2005, NREA published a
new Invitation for
Prequalification, to be submitted by November 8th 2005. 2005
Download the Egypt START Mission Report (PDF
2.918 kB)
 |