India

Home
Up
Algeria
Australia
Brazil
Egypt
Greece
India
Iran
Israel
Italy
Jordan
Mexico
Morocco
South Africa
Spain
USA

 CSP Project Developments in India

Map of India

Beginning in the 1980s, energy planners reviewed options for parabolic trough, solar thermal power stations in developing countries. However, this renewable energy technology, particularly suitable for tropical developing countries with stable and intensive degrees of solar insolation, was first introduced in industrialized country power markets. More than 300 megawatts (MW) of active solar thermal power capacity were installed in California in the early 1980s. In 1994, the Indian government commissioned a site specific feasibility study for a 35 MW power plant to be situated in arid Mathania, Rajasthan, near Jodhpur. This study became the subject of further review by engineering consultants engaged by the state government of Rajasthan and was supplemented by technical options assessments conducted in 1996 with the assistance of the German bank KfW. As the outcomes of these assessments and solar field performance reviews were favorable, the Rajasthan government decided to pursue the first commercial-scale, solar thermal investment in a developing country and invited KfW and the GEF to support this pioneering undertaking. The main objectives of the Mathania project were:

  • (a) to demonstrate the operational viability of parabolic trough, solar thermal power generation in India;

  • (b) promote commercial development of solar thermal technology and cost reduction; and

  • (c) help reduce greenhouse gas global emissions in the short and longer term.

Operational viability was to be demonstrated through operation of a solar thermal plant by an independent power producer which should sell power to the utility through commercial power sales and contracts. The Mathania project concept entered the GEF work program in 1996. With a GEF contribution of US$49 million and a total financing volume of US$245 million (co-financed by the government of India and KfW, and executed by KfW), it was one of the largest of some 82 GEF sponsored energy investments.

The prequalification of potential Contractors had been conducted in 2001.  At that time there was little interest from international Combined Cycle Companies to involve themselves in solar technologies.  (This however has later changed considerably.)  Only three Consortia were prequalified, and the only one Consortia under international leadership later on declined to bid.  This left only two Bidders (the Indian companies BHEL and Larsen & Toubro).  Both Bidders had the same Solar Subcontractor (SOLEL). 

Due to internal difficulties neither of the two Consortia did manage to submit a Bid.  After several prolongations the bidding process was terminated in late 2003, and it was decided to reopen the Bidding also for new Bidders.  By that time new International Consortia had shown interest and were ready to enter the Bidding.  It was also decided to change the approach to an “and/or” approach (Bidding for ISCC and/or Bidding for the Solar Island and/or Bidding for Combined Cycle Island) in order to improve the competitive situation.  In February 2004 Fichtner Solar GmbH was assigned the task to modify the Bid Document (RfP) accordingly. 

Before the Bid Document (RfP) could have been issued by the middle of 2004, the World Bank requested, that the Indian Government reconfirm the commitment of all involved public authorities towards the project.  The discussions within India to get this “all-Indian-commitment” are currently ongoing.

 

 

[Home] [Contents] [Search]