Mexico's Comisión Federal de
Electricidad (CFE) issued a Request for Proposals in March 2002 for a 250 MW
gas-fired combined cycle plant with an optional integrated parabolic trough
solar field of at least 25 MW electrical output. The incremental solar costs
should be covered by a grant from
GEF. As investor’s response to this
concept was very limited, it was decided in 2003, that an EPC scheme with
CFE as GEF grant recipient should be pursued. The solar field would no
longer be an option but compulsory. In 2005 the plant location was changed
to Sonora State and it was suggested by CFE to double the combined cycle
size from 250 to 500MW. |