Home » Latest In: » CSP News Briefs » Xinjiang’s Turpan Wustong 1GW CSP + PV expected completion in 2026

Follow

follow us in feedly

Share

Xinjiang’s Turpan Wustong 1GW CSP + PV expected completion in 2026

March 24, 2026

Source: Jennifer Zhang, Editor in Chief ESPLAZA and CSPPlaza at LinkedIn

The Wustong CSP + PV Hybrid Project in Tokson County, Turpan City, is one of the key market-oriented renewable energy projects approved in the second batch of Xinjiang Uygur Autonomous Region in 2022.

It is also a flagship project under Turpan’s 14th Five-Year Plan for new energy development and a major demonstration project within Eastern Xinjiang’s large-scale renewable energy base.

Project Overview

The project is located in the Wustonggou area of Tokson County, Turpan City, approximately 6 km south of Provincial Highway S301 and north of the Wustonggou Reservoir, about 48 km from the county center. Situated in a Gobi region with abundant solar resources, the site offers excellent conditions for concentrated solar power (CSP) development.

The project has a total installed capacity of 1GW, comprising:

  • 100MW molten salt tower CSP plant (core component)
  • 900MW photovoltaic (PV) capacity

Technical Configuration

The project adopts a mature molten salt tower CSP technology:

  • 14,680 heliostats, each measuring 6.3m Ă— 4.8m
  • Total reflective area: 440,400 m²
  • 8-hour thermal energy storage system
  • One set each of high-temperature and low-temperature molten salt tanks
  • Total molten salt inventory: approximately 21,000 tonnes

This configuration enables long-duration energy storage, stable power output, and efficient integration of variable renewable energy.

Construction Progress

  • 2022: Included in Xinjiang’s second batch of market-oriented grid-connected renewable energy projects, marking project initiation.
  • July 31, 2023: Cosin Solar Technology Co., Ltd. awarded the contract for the CSP solar field system, confirming core technology and equipment supplier.
  • September 2023: Official groundbreaking; main civil construction commenced.
  • January 2024:450MW of PV modules installed220kV #1 booster station commissioned for trial operationCSP civil works reached 60% completion; receiver tower construction reached 60m height
  • November 2024: All 14,680 heliostats installed, completing a key milestone for the solar field
  • April 2025: Final design technical briefing and construction drawing review completed; project entered full-scale construction and installation phase
  • July 8, 2025: Steam turbine casing closure completed, marking a critical milestone for the conventional island
    September 18, 2025: Distributed Control System (DCS) energized and restored; project entered integrated system commissioning phase
    December 1, 2025: Water filling test for molten salt tanks completed; key thermal storage system acceptance milestone achieved
    January 20, 2026: Insulation works for molten salt tanks completed
    February 2026: Jiangsu Lianchu Energy Technology shortlisted for molten salt commissioning works; salt melting expected to be completed by
    April 30, 2026

Read More: Jennifer Zhang, Editor in Chief ESPLAZA and CSPPlaza at LinkedIn

Latest In:

CSP News & Analysis

SolarPACES Announcements
CSP News Briefs
CSP Tech Explainers