Source: email from Sunny Sun; CSPFocus
China Three Gorges New Energy has issued the bidding announcement on the EPC of two 100MW CSP projects, both are located in Qinghai province, northwest of China. According to the announcement (in Chinese), both projects are planned to start on July 1st 2022, and completed in full capacity by Nov 30th 2023. Bidders are required at least one 50MW CSP project reference since 2017. A consertia bidder is accepted.
Bid document claim time: from 9am June 9th, 2022 to 5pm June 15th, 2022.
Bid submission and opening: 10am June 29th, 2022.
Find below a list of upcoming CSP Projects totaling 1.3 GW:
[Ed Note: this tariff is the equivalent of 4.8 cents /kWh in USD]